Downtime you cannot explain is downtime you will repeat
Most plants know roughly how many hours their machines were down last month. Far fewer know why. Without the why, every stop is a one-off: fixed, forgotten, and back three weeks later. Tracking downtime by cause turns a pile of stops into a short list of things to fix.
Decide what counts as downtime
Write the rules down once and keep them the same every month:
- A stop counts from the moment the machine is taken out of service (locked out) to the moment it is handed back (released), not from when someone noticed it.
- Planned maintenance is downtime too, but keep it apart from failures, so servicing a machine well does not make it look unreliable.
- A machine sitting idle with no work is a production loss (it shows in OEE), not maintenance downtime. Keep the two apart.
- A machine taken out of service for good has left the count; it is not down.
Keep the list of causes short
A list of forty causes gets ignored or filled with the first one in the menu. Eight words the shop floor already uses work better. For example:
- Mechanical
- Electrical
- Coolant / hydraulic
- Tooling
- Control / software
- Waiting for parts
- Planned maintenance
- Other, with a note saying what
Record the cause when the machine goes back into service
The best moment is the release: the person handing the machine back knows what was wrong and what was done. At the end of the month nobody remembers. Make the cause required at release, and let “Other” through only with a note.
Waiting for parts deserves its own cause. It is often a large share of the hours, and its fix is in purchasing and stores, not on the machine.
Stops recorded before you started asking for causes should be labelled from what the record shows (a rule trip, an emergency order, a planned order) or marked not recorded. Never guess them after the fact.
Read it as a Pareto chart
Sort the causes by hours lost, largest first, and draw the running total as a line. In most plants a few causes carry most of the hours.
An example, with made-up figures: a plant lost 42 hours in a month. Mechanical 18 hours, waiting for parts 11, electrical 6, tooling 4, other 3. The first two causes are 69 % of the hours, so they are where next month's effort goes.
Count the stops per cause and their average repair time (MTTR) as well. Many short stops and a few long ones need different fixes: the first is usually a recurring fault, the second a slow repair or a missing spare.
How Atlas Edge does it
In Atlas Edge a stop is a lockout under a work order, and releasing it asks for its cause from the list above (“Other” needs a note). Downtime by cause is shown per machine, area and plant as a Pareto chart: bars for each cause's share of the hours, a line for the running total. The hours of all causes add up to the locked-out time in the availability figure, and each cause shows its stops and its MTTR. The monthly report's Excel workbook has a Downtime sheet with the same figures, as formulas you can check.