The formula
Overall equipment effectiveness compares what a machine made with what it could have made in the time it was meant to run. It is three ratios multiplied together:
- Availability = run time / planned production time
- Performance = (ideal cycle time × total parts) / run time
- Quality = good parts / total parts
- OEE = availability × performance × quality, which works out to ideal cycle time × good parts / planned production time
A worked example
An example, with made-up figures: a CNC machine is planned for one 8-hour shift with a 30-minute break, so planned production time is 450 minutes. It ran for 360 of them. Its ideal cycle time is 2 minutes a part, it made 150 parts, and 6 were rejected.
Availability = 360 / 450 = 80 %. Performance = (2 × 150) / 360 = 83.3 %. Quality = 144 / 150 = 96 %. OEE = 0.80 × 0.833 × 0.96 = 64 %. Check: 2 × 144 / 450 = 64 %.
Where each input should come from
- Planned production time: the shift calendar, less breaks. Not 24 hours, and not just the hours someone remembers.
- Run time: measured, not typed in. A minute counts as running when the machine draws a real share of its rated power.
- Ideal cycle time: the best the machine can do for that part, from its specification or a proven best, not the average of last month.
- Total and reject counts: the machine's own part counter, and a reject counter or entry. Counter resets and gaps must not be bridged by guessing.
Mistakes that make OEE look better than it is
Most OEE figures that look too good have one of these in them:
- Hours with no data counted as zero downtime. If the gateway was offline, that time is unknown, not good. It should be reported as unrecorded and left out.
- Using the average cycle time instead of the ideal one, which hides every slow cycle.
- Taking planned time only from the hours the machine ran.
- Counting parts from one period against run time from another.
- Calling maintenance availability (time not locked out) OEE availability (run time against planned time). They answer different questions; keep both, named apart.
The same formula in ISO 22400 terms
ISO 22400-2 defines OEE for manufacturing operations management with its own names for the times and counts. They map one to one onto the shop-floor words, which helps when a customer or an auditor asks which definition you use.
| ISO 22400-2 | Abbreviation | Shop-floor word |
|---|---|---|
| Planned busy time | PBT | Planned production time (shift less planned breaks) |
| Actual production time | APT | Run time |
| Planned run time per item | PRI | Ideal cycle time |
| Produced quantity | PQ | Total parts |
| Good quantity | GQ | Good parts |
| Availability = APT / PBT | A | Availability |
| Effectiveness = PRI × PQ / APT | E | Performance |
| Quality ratio = GQ / PQ | QR | Quality |
Where the six big losses land
Every lost minute falls into exactly one of the three ratios. Sorting losses this way tells you which ratio to work on:
| Loss | Example | Lowers |
|---|---|---|
| Breakdowns | Spindle bearing failure, drive fault | Availability |
| Setups and adjustments | Changeover, first-off inspection | Availability |
| Small stops | Chip jam cleared in a minute, sensor blocked | Performance |
| Reduced speed | Feed override at 80 %, worn tool run slower | Performance |
| Start-up rejects | Parts scrapped while the machine warms up | Quality |
| Production rejects | Out-of-tolerance parts, rework | Quality |
Edge cases that change the answer
- Several part types in one shift: performance must weight each part by its own ideal cycle time (sum of ideal cycle time × count over all parts, divided by run time), not one average cycle time.
- Changeovers: decide once whether a planned changeover is planned time. Most plants keep it in planned time so it shows up as an availability loss and gets worked on.
- No work scheduled: a shift with no orders is not planned time. Leave it out rather than reporting a zero availability.
- Rework: a part that passes only after rework is not a good part in the quality ratio, unless you report first-pass yield separately and say so.
- Performance over 100 %: the ideal cycle time is set too long or counts and times come from different periods. Fix the input; do not cap the result.
- A machine with no part counter: availability can still be measured from power; performance and quality cannot, and OEE should be left empty with that reason.
How Atlas Edge calculates it
Atlas Edge calculates OEE per machine, day and month on exactly this time model: planned time from the shift calendar in its settings, run time from measured power, counts from the machines' part and reject counters, and the ideal cycle time on each machine's record. An hour whose running minutes are not known is reported as unrecorded, and any figure missing an input is left empty with the reason in words. The monthly report's workbook shows the formulas, so anyone can check them in Excel.