Skip to content

KPIs

How to calculate OEE honestly.

OEE = availability × performance × quality. A worked example, where each input comes from, and the common mistakes (missing data as zero, the wrong cycle time, the wrong planned time) that make OEE look better than the floor is.

4 min read · Updated 24 November 2026

The formula

Overall equipment effectiveness compares what a machine made with what it could have made in the time it was meant to run. It is three ratios multiplied together:

  • Availability = run time / planned production time
  • Performance = (ideal cycle time × total parts) / run time
  • Quality = good parts / total parts
  • OEE = availability × performance × quality, which works out to ideal cycle time × good parts / planned production time

A worked example

An example, with made-up figures: a CNC machine is planned for one 8-hour shift with a 30-minute break, so planned production time is 450 minutes. It ran for 360 of them. Its ideal cycle time is 2 minutes a part, it made 150 parts, and 6 were rejected.

Availability = 360 / 450 = 80 %. Performance = (2 × 150) / 360 = 83.3 %. Quality = 144 / 150 = 96 %. OEE = 0.80 × 0.833 × 0.96 = 64 %. Check: 2 × 144 / 450 = 64 %.

Where each input should come from

  • Planned production time: the shift calendar, less breaks. Not 24 hours, and not just the hours someone remembers.
  • Run time: measured, not typed in. A minute counts as running when the machine draws a real share of its rated power.
  • Ideal cycle time: the best the machine can do for that part, from its specification or a proven best, not the average of last month.
  • Total and reject counts: the machine's own part counter, and a reject counter or entry. Counter resets and gaps must not be bridged by guessing.

Mistakes that make OEE look better than it is

Most OEE figures that look too good have one of these in them:

  • Hours with no data counted as zero downtime. If the gateway was offline, that time is unknown, not good. It should be reported as unrecorded and left out.
  • Using the average cycle time instead of the ideal one, which hides every slow cycle.
  • Taking planned time only from the hours the machine ran.
  • Counting parts from one period against run time from another.
  • Calling maintenance availability (time not locked out) OEE availability (run time against planned time). They answer different questions; keep both, named apart.

The same formula in ISO 22400 terms

ISO 22400-2 defines OEE for manufacturing operations management with its own names for the times and counts. They map one to one onto the shop-floor words, which helps when a customer or an auditor asks which definition you use.

ISO 22400-2 names and the shop-floor words used in this guide
ISO 22400-2AbbreviationShop-floor word
Planned busy timePBTPlanned production time (shift less planned breaks)
Actual production timeAPTRun time
Planned run time per itemPRIIdeal cycle time
Produced quantityPQTotal parts
Good quantityGQGood parts
Availability = APT / PBTAAvailability
Effectiveness = PRI × PQ / APTEPerformance
Quality ratio = GQ / PQQRQuality

Where the six big losses land

Every lost minute falls into exactly one of the three ratios. Sorting losses this way tells you which ratio to work on:

The six big losses of TPM and the OEE ratio each one lowers
LossExampleLowers
BreakdownsSpindle bearing failure, drive faultAvailability
Setups and adjustmentsChangeover, first-off inspectionAvailability
Small stopsChip jam cleared in a minute, sensor blockedPerformance
Reduced speedFeed override at 80 %, worn tool run slowerPerformance
Start-up rejectsParts scrapped while the machine warms upQuality
Production rejectsOut-of-tolerance parts, reworkQuality

Edge cases that change the answer

  • Several part types in one shift: performance must weight each part by its own ideal cycle time (sum of ideal cycle time × count over all parts, divided by run time), not one average cycle time.
  • Changeovers: decide once whether a planned changeover is planned time. Most plants keep it in planned time so it shows up as an availability loss and gets worked on.
  • No work scheduled: a shift with no orders is not planned time. Leave it out rather than reporting a zero availability.
  • Rework: a part that passes only after rework is not a good part in the quality ratio, unless you report first-pass yield separately and say so.
  • Performance over 100 %: the ideal cycle time is set too long or counts and times come from different periods. Fix the input; do not cap the result.
  • A machine with no part counter: availability can still be measured from power; performance and quality cannot, and OEE should be left empty with that reason.

How Atlas Edge calculates it

Atlas Edge calculates OEE per machine, day and month on exactly this time model: planned time from the shift calendar in its settings, run time from measured power, counts from the machines' part and reject counters, and the ideal cycle time on each machine's record. An hour whose running minutes are not known is reported as unrecorded, and any figure missing an input is left empty with the reason in words. The monthly report's workbook shows the formulas, so anyone can check them in Excel.

Sources

Guide

Quick answers.

What is a good OEE score?

85 % is often quoted as world class for discrete manufacturing, and many plants measure well below 60 % once they measure honestly. The trend on your own machines matters more than any benchmark.

What is the formula for OEE?

OEE = availability × performance × quality, where availability = run time / planned production time, performance = ideal cycle time × total count / run time, and quality = good count / total count.

Should missing data count as downtime?

Neither as downtime nor as uptime. Time with no readings is unknown; report it as unrecorded and leave it out, or the OEE you report is a guess.