How to measure machine utilisation (utilization, in US spelling) from what each machine draws: when a minute counts as running, idle or off, why missing data must never count as off, what to do for machines without a meter, and how to turn the minutes into a utilisation figure you can trust.

2 min read · Updated 24 November 2026

Utilisation is a count of minutes

Ask a shop how busy its machines are and you will hear a guess. Utilisation replaces the guess with a count: of the hours a machine could have worked, how many did it actually spend working? The hard part is not the division. It is deciding, minute by minute, what “working” means, and doing it the same way on every machine.

Read the state from power

A machine's power draw says what it is doing without anyone writing anything down. Compare each minute's average power with the machine's rated power. With a common split like this one, three states fall out:

  • Running: at least 10 % of rated power. The spindle, the pump or the drive is doing work.
  • Idle: above 2 % and below 10 %. Powered up and waiting: hydraulics, coolant and drives on, no cut.
  • Off: at or below 2 %. Control power only, or nothing.
An example: the thresholds for a machine rated 15 kW
StateShare of rated powerAverage power in the minute
Running10 % or more1.5 kW or more
Idleabove 2 %, below 10 %above 0.3 kW, below 1.5 kW
Off2 % or less0.3 kW or less

Missing data is not off

When a meter or a gateway stops reporting, the tempting shortcut is to treat the silence as the machine being off. It quietly lowers utilisation for reasons that have nothing to do with production. Keep a separate state for minutes with no reading, and show it as no data.

Time the machine was locked out for maintenance, or taken out of service, is not idle either. Take it from the lockout record, so it overrides whatever the power reading says.

Machines without a power meter

Many CNC controllers and PLCs already report what they are doing: running, idle, feed hold, stopped on an alarm, emergency stop. Where there is no power reading, use that instead: running counts as running, off as off, and everything in between as idle. Where both are read, prefer power: it shows a machine that is “in cycle” but not cutting.

Calculate utilisation

Run hours = running minutes / 60. Utilisation % = run hours / uptime hours × 100, where uptime is the time the machine was available: the period, minus the time it was locked out or out of service. Dividing by uptime rather than by the calendar keeps breakdowns out of the utilisation figure; they belong in availability.

An example, with made-up figures: in a 30-day month (720 hours) a grinder was locked out for 20 hours, so its uptime was 700 hours. It ran for 385 of them. Utilisation = 385 / 700 = 55 %.

Hours with no reading at all should stay unknown in the figures, not count as zero. A utilisation figure is only as good as the share of hours it was measured on, so show that share beside it.

How Atlas Edge does it

Atlas Edge sorts every minute of every connected machine into Running, Idle, Off, Locked out, Decommissioned or No data, from its power against its rating, the controller's run state for machines read without a meter, and the lockout record overriding both. Run hours, utilisation (run hours over uptime) and a state timeline per machine and for the plant are on the Maintenance KPIs view, and the monthly Excel report has the state hours per day. Hours without data are shown as “No data recorded”, never as 0.

Guide

Quick answers.

What is a good machine utilisation?

There is no single figure: it depends on shifts, product mix and how many machines a shop keeps for peaks. Compare a machine with its own past months and with machines doing the same work, and look at what fills its idle time.

What is the difference between utilisation and OEE?

Utilisation says how much of its available time a machine spent running. OEE goes further: of the planned production time, how much was spent making good parts at the ideal speed. A machine can run all day and still have a low OEE if it runs slowly or makes scrap.

Is idle time the same as downtime?

No. Idle time is when a machine could run but does not: no job, no operator, no material. Downtime is when it cannot run because it is broken or being serviced. Keep them apart: idle time is a production question, downtime a maintenance one.

More guides

Bring your plant alive.

A gateway per shop area, the controllers you already have, and your first monthly report in the inbox on the 1st. Tell us about your floor.