OEE calculator, with the working shown.

Type a shift's planned time, stops, ideal cycle time and part counts, and see availability, performance, quality and OEE, with the check figure and a plain note when an input cannot be right.

2 min read · Updated 24 November 2026

OEE calculator

Type your own figures. It works in your browser: nothing is sent or saved.

Availability
–
Performance
–
Quality
–
OEE
–

What to type in

  • Shift length and planned breaks: planned production time is the shift less its planned breaks. A shift with no work scheduled is not planned time at all.
  • Stopped during planned time: every minute the machine was not running when it was meant to be, whether a breakdown, a setup or waiting for material.
  • Ideal cycle time: the best the machine can do for this part, in seconds, from its specification or a proven best run. Not last month's average.
  • Parts made and rejected: from the machine's counter if it has one. Rejected includes scrap and parts that needed rework.

Reading the result

The calculator multiplies the three ratios and also works OEE out the short way, ideal cycle time × good parts / planned time. The two must agree; if they do not, an input is in the wrong unit.

If performance comes out above 100 %, the ideal cycle time is longer than the machine really needs, or the part count belongs to a different period. It says so rather than hiding it behind a cap.

Three example shifts, made-up figures: same machine, different losses
ShiftAvailabilityPerformanceQualityOEE
A: long breakdown60.0 %95.0 %99.0 %56.4 %
B: slow running92.0 %70.0 %99.0 %63.8 %
C: scrap after a tool change92.0 %95.0 %85.0 %74.3 %

What a good number is

85 % is often quoted as world class for discrete manufacturing. Plants that start measuring from real machine data commonly find themselves far lower, and that is normal: an honest 55 % that improves is worth more than a 90 % built on typed-in run times.

Compare a machine with itself over time, and compare the three ratios rather than the total. The example above shows why: shifts B and C have similar OEE for completely different reasons.

Doing it every shift without a spreadsheet

Atlas Edge works OEE out per machine, day and month from the shift calendar in its settings, run time measured from power, the machines' part and reject counters, and the ideal cycle time on each machine's record. Hours it has no readings for are reported as unrecorded, not as running, and the monthly Excel workbook carries the same formulas so anyone can check them.

Sources

Guide

Quick answers.

How do you calculate OEE?

OEE = availability × performance × quality. Availability = run time / planned production time; performance = ideal cycle time × total parts / run time; quality = good parts / total parts. The product equals ideal cycle time × good parts / planned production time.

Should breaks count in planned production time?

No. Planned breaks are taken out before the calculation. Unplanned stops, setups and waiting stay in, as availability losses.

Is my data sent anywhere?

No. The calculator runs in your browser; nothing you type is sent or stored.

More guides

Bring your plant alive.

A gateway per shop area, the controllers you already have, and your first monthly report in the inbox on the 1st. Tell us about your floor.